A special use permit shall become null and void in any of the following cases:

A. If a site plan or architectural review, as applicable, is not approved within 12 months of the date of permit approval.

B. If an approved site plan, architectural review application, or building permit expires.

C. If a building permit is not issued within two years of the date of approval, in cases where a corresponding site plan or architectural review is not required.

D. If a substantial violation of the conditions of the permit, as determined by the Planning Director or designee occurs. The addition of language to the special use permit regarding such voiding shall not be required.

E. Validity may be extended if vesting is determined per Sec. 3.20, Vested Rights.